Supply water to a dry machine on an upper floor

At a dry machine, read its litres-per-minute requirement and any message saying how far above water reach it sits. Follow the pipe to the well, then press E at a sight glass or pump and use SHOW PIPE PRESSURE RADIUS. A well lifts water 10 m; insert Pipe Pump Mk.1 or Mk.2 into the main for 20 m or 50 m of additional lift. If height is covered but flow is short, check supply, valves and competing branches rather than adding more pipe.

Updated 2026-11-17 · Early Access • V16.4 rules

On this page

Follow the route

  1. Unlock and recognise the water system

    The Dairy opens the Borehole Pump, water pipes and Biogas Digester on the V15.4 progression. Open BUILDER → WATER, equip Water Pipe, click the shiny flange on the supplying machine, then click the flange on the receiving machine. Both pipe ends must attach to a flange. Connect the well to a readable main and branch to the consumer’s water intake. Water, belts and power are separate connections; a powered machine can still be dry.

    The Water Pipe build card, showing the pipe and instructions to click a shiny flange on each machine.Open full-size image ↗
    Wobble Pop Gaming, EA V16.4 at 41:40. The actual card specifies both endpoints must be on a flange.
  2. Identify the machine connection

    The silver pipe flanges are separate from the belt and power connectors. Click the actual flange on each machine rather than the nearby body or floor. Follow the new pipe end to end before diagnosing pressure.

    Water pipe placement at two Hay Pulpers, with the low silver flanges visible.Open full-size image ↗
    Wobble Pop Gaming, EA V16.4 at 42:00. Real pipe connection geometry; not a measured yard plan.
  3. Read the machine before moving it

    A machine with no water glows blue. Its panel states the required litres per minute; if it is above the network’s reach, the status also reports the height shortfall. Note that shortfall so you solve head rather than repeatedly extending the same pipe.

  4. Open the pressure view

    Press E at the pipe’s sight glass or on a pump. The water plate shows pressure and flow. Enable SHOW PIPE PRESSURE RADIUS and find the ring where the water stops climbing. Inspect the actual consumer’s location against that reach before connecting another upper-floor branch.

  5. Add the appropriate pump stage

    A well alone pushes water 10 m up. Cut Pipe Pump Mk.1 into the main for 20 m of additional lift, or Mk.2 for 50 m. These inline pumps push either way round; turning one around is not the fix for a missing height allowance. Recheck the pressure view after placing it and confirm the formerly dry consumer is now in reach.

    Water head components
    PartLift contributionAction
    Well / Borehole Pump10 mStart the supply network here.
    Pipe Pump Mk.1+20 mInsert into the main where more lift is needed.
    Pipe Pump Mk.2+50 mUse for a larger rise.
    ValveFlow cap, not extra heightCheck it when pressure reach is adequate but supply is restricted.
  6. Resolve flow starvation separately

    If the height is covered, check water arriving at the well/pump, the pipe connections and each valve on the affected branch. Read the consumers’ displayed demand and compare it with actual flow. A valve limits what can pass; opening the wrong branch can leave another short. Use one readable main with accessible branch valves rather than a hard-to-trace mesh.

  7. Keep water-fed power equipment supplied

    Give the pump support chain a high power priority. The Biogas Digester and Gas Plant warn and count down as water runs out. For a Digester, inspect the wrapped-bale feed as well: a shortage of fuel and a shortage of water are different repairs. After restoring both, watch it return to sustained generation.

  8. Extend upward without hiding the service points

    Pipes can pass straight through platforms. Keep the riser by an accessible aisle, leave pumps and sight glasses reachable, and check the radius before adding the next consumer. Use colours to distinguish multiple networks. V16.4 lets a tee water splitter fit at the Borehole Pump outlet.

Completion check

Check the result

The consumer is inside the displayed pressure reach, receives its required flow and no longer reports dry. Water-fed generators stay supplied under load.

If it still fails

If it is still dry above the ring, add a pump stage or lower the consumer. If it is in reach but starved, trace valves, branch demand and supply. If the water system loses power, restore its circuit; do not treat a blue water warning as proof that a belt needs rebuilding.